summaryrefslogtreecommitdiffstats
path: root/docs/requirements
diff options
context:
space:
mode:
authorLiyi Meng <liyi.meng@ericsson.com>2016-03-14 14:34:12 +0100
committerLiyi Meng <liyi.meng@ericsson.com>2016-05-27 15:21:28 +0200
commit9ba9270d8373d6d4bb3d34ae6c618e9b5f937d63 (patch)
tree243be729bd85b12e939abdea3fb4dd518a61f735 /docs/requirements
parent083979fb4bf47784a727eddac1f4f01d6da0e093 (diff)
Upgrade duration requirement
We summary previous discussions on upgrade duration, and define the requirements on upgrade from time perspective. Change-Id: I4b14f58c313f8340b2203d7a08f244b67a79a692 Signed-off-by: Liyi Meng <liyi.meng@ericsson.com>
Diffstat (limited to 'docs/requirements')
-rw-r--r--docs/requirements/104-Requirements.rst210
1 files changed, 36 insertions, 174 deletions
diff --git a/docs/requirements/104-Requirements.rst b/docs/requirements/104-Requirements.rst
index b6e7f57..3dd66dc 100644
--- a/docs/requirements/104-Requirements.rst
+++ b/docs/requirements/104-Requirements.rst
@@ -5,180 +5,42 @@ Requirements
Upgrade duration
================
-As the OPNFV end-users are primarily Telecom operators, the network
-services provided by the VNFs deployed on the NFVI should meet the
-requirement of 'Carrier Grade'.::
-
- In telecommunication, a "carrier grade" or"carrier class" refers to a
- system, or a hardware or software component that is extremely reliable,
- well tested and proven in its capabilities. Carrier grade systems are
- tested and engineered to meet or exceed "five nines" high availability
- standards, and provide very fast fault recovery through redundancy
- (normally less than 50 milliseconds). [from wikipedia.org]
-
-"five nines" means working all the time in ONE YEAR except 5'15".
-
-::
-
- We have learnt that a well prepared upgrade of OpenStack needs 10
- minutes. The major time slot in the outage time is used spent on
- synchronizing the database. [from ' Ten minutes OpenStack Upgrade? Done!
- ' by Symantec]
-
-This 10 minutes of downtime of the OpenStack services however did not impact the
-users, i.e. the VMs running on the compute nodes. This was the outage of
-the control plane only. On the other hand with respect to the
-preparations this was a manually tailored upgrade specific to the
-particular deployment and the versions of each OpenStack service.
-
-The project targets to achieve a more generic methodology, which however
-requires that the upgrade objects fulfil certain requirements. Since
-this is only possible on the long run we target first the upgrade
-of the different VIM services from version to version.
-
-**Questions:**
-
-1. Can we manage to upgrade OPNFV in only 5 minutes?
-
-.. <MT> The first question is whether we have the same carrier grade
- requirement on the control plane as on the user plane. I.e. how
- much control plane outage we can/willing to tolerate?
- In the above case probably if the database is only half of the size
- we can do the upgrade in 5 minutes, but is that good? It also means
- that if the database is twice as much then the outage is 20
- minutes.
- For the user plane we should go for less as with two release yearly
- that means 10 minutes outage per year.
-
-.. <Malla> 10 minutes outage per year to the users? Plus, if we take
- control plane into the consideration, then total outage will be
- more than 10 minute in whole network, right?
-
-.. <MT> The control plane outage does not have to cause outage to
- the users, but it may of course depending on the size of the system
- as it's more likely that there's a failure that needs to be handled
- by the control plane.
-
-2. Is it acceptable for end users ? Such as a planed service
- interruption will lasting more than ten minutes for software
- upgrade.
-
-.. <MT> For user plane, no it's not acceptable in case of
- carrier-grade. The 5' 15" downtime should include unplanned and
- planned downtimes.
-
-.. <Malla> I go agree with Maria, it is not acceptable.
-
-3. Will any VNFs still working well when VIM is down?
-
-.. <MT> In case of OpenStack it seems yes. .:)
-
-The maximum duration of an upgrade
-^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
-
-The duration of an upgrade is related to and proportional with the
-scale and the complexity of the OPNFV platform as well as the
-granularity (in function and in space) of the upgrade.
-
-.. <Malla> Also, if is a partial upgrade like module upgrade, it depends
- also on the OPNFV modules and their tight connection entities as well.
-
-.. <MT> Since the maintenance window is shrinking and becoming non-existent
- the duration of the upgrade is secondary to the requirement of smooth upgrade.
- But probably we want to be able to put a time constraint on each upgrade
- during which it must complete otherwise it is considered failed and the system
- should be rolled back. I.e. in case of automatic execution it might not be clear
- if an upgrade is long or just hanging. The time constraints may be a function
- of the size of the system in terms of the upgrade object(s).
-
-The maximum duration of a roll back when an upgrade is failed
-^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
-
-The duration of a roll back is short than the corresponding upgrade. It
-depends on the duration of restore the software and configure data from
-pre-upgrade backup / snapshot.
-
-.. <MT> During the upgrade process two types of failure may happen:
- In case we can recover from the failure by undoing the upgrade
- actions it is possible to roll back the already executed part of the
- upgrade in graceful manner introducing no more service outage than
- what was introduced during the upgrade. Such a graceful roll back
- requires typically the same amount of time as the executed portion of
- the upgrade and impose minimal state/data loss.
-
-.. <MT> Requirement: It should be possible to roll back gracefully the
- failed upgrade of stateful services of the control plane.
- In case we cannot recover from the failure by just undoing the
- upgrade actions, we have to restore the upgraded entities from their
- backed up state. In other terms the system falls back to an earlier
- state, which is typically a faster recovery procedure than graceful
- roll back and depending on the statefulness of the entities involved it
- may result in significant state/data loss.
-
-.. <MT> Two possible types of failures can happen during an upgrade
-
-.. <MT> We can recover from the failure that occurred in the upgrade process:
- In this case, a graceful rolling back of the executed part of the
- upgrade may be possible which would "undo" the executed part in a
- similar fashion. Thus, such a roll back introduces no more service
- outage during an upgrade than the executed part introduced. This
- process typically requires the same amount of time as the executed
- portion of the upgrade and impose minimal state/data loss.
-
-.. <MT> We cannot recover from the failure that occurred in the upgrade
- process: In this case, the system needs to fall back to an earlier
- consistent state by reloading this backed-up state. This is typically
- a faster recovery procedure than the graceful roll back, but can cause
- state/data loss. The state/data loss usually depends on the
- statefulness of the entities whose state is restored from the backup.
-
-The maximum duration of a VNF interruption (Service outage)
-^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
-
-Since not the entire process of a smooth upgrade will affect the VNFs,
-the duration of the VNF interruption may be shorter than the duration
-of the upgrade. In some cases, the VNF running without the control
-from of the VIM is acceptable.
-
-.. <MT> Should require explicitly that the NFVI should be able to
- provide its services to the VNFs independent of the control plane?
-
-.. <MT> Requirement: The upgrade of the control plane must not cause
- interruption of the NFVI services provided to the VNFs.
-
-.. <MT> With respect to carrier-grade the yearly service outage of the
- VNF should not exceed 5' 15" regardless whether it is planned or
- unplanned outage. Considering the HA requirements TL-9000 requires an
- end-to-end service recovery time of 15 seconds based on which the ETSI
- GS NFV-REL 001 V1.1.1 (2015-01) document defines three service
- availability levels (SAL). The proposed example service recovery times
- for these levels are:
-
-.. <MT> SAL1: 5-6 seconds
-
-.. <MT> SAL2: 10-15 seconds
-
-.. <MT> SAL3: 20-25 seconds
-
-.. <Pva> my comment was actually that the downtime metrics of the
- underlying elements, components and services are small fraction of the
- total E2E service availability time. No-one on the E2E service path
- will get the whole downtime allocation (in this context it includes
- upgrade process related outages for the services provided by VIM etc.
- elements that are subject to upgrade process).
-
-.. <MT> So what you are saying is that the upgrade of any entity
- (component, service) shouldn't cause even this much service
- interruption. This was the reason I brought these figures here as well
- that they are posing some kind of upper-upper boundary. Ideally the
- interruption is in the millisecond range i.e. no more than a
- switch-over or a live migration.
-
-.. <MT> Requirement: Any interruption caused to the VNF by the upgrade
- of the NFVI should be in the sub-second range.
-
-.. <MT]> In the future we also need to consider the upgrade of the NFVI,
- i.e. HW, firmware, hypervisors, host OS etc.
+Being a telecom service system, OPNFV shall target at carrier grade availability,
+which allows only about 5 minutes of outage in a year. Base on this basic input
+and discussions on the current solutions, The following requirements are defined
+from the perspective of time constraints:
+
+- OPNFV platform must be deployed with HA to allow live upgrade possible. Considering of
+ the scale, complexity, and life cycle of OPNFV system, allocating less than
+ 5 minutes out of a year for upgrade is in-realistic. Therefore OPNFV should
+ be deployed with HA, allowing part of system being upgraded, while its
+ redundant parts continue to serve End-User. This hopefully relieves the time
+ constraint on upgrade operation to achievable level.
+
+- VNF service interruption for each switching should be sub-second range. In
+ HA system, switching from an in-service system/component to the redundant
+ ones normally cause service interruption. From example live-migrating a
+ virtual machine from one hypervisor to another typically take the virtual
+ machine out of service for about 500ms. Summing up all these interruptions in
+ a year shall be less than 5 minutes in order to fulfill the five-nines carrier
+ grade availability. In addition, when interruption goes over a second, End-User
+ experience is likely impacted. This document therefore recommends service
+ switching should be less than a second.
+
+- VIM interruption shall not result in NFVI interruption. VIM in general has more
+ logic built-in, therefore more complicated, and likely less reliable than NFVI.
+ To minimize the impact from VIM to NFVI, unless VIM explicitly order NFVI stop
+ functioning, NFVI shall continue working as it should.
+
+- Total upgrade duration should be less than 2 hours. Even time constraint is
+ relieved with HA design, the total time for upgrade operation is recommended
+ to limit in 2 hours. The reason is that upgrade might interfere End-User
+ unexpectedly, shorter maintenance window is less possible risk. In this
+ document, upgrade duration is started at the moment that End-User services
+ are possibly impacted to the moment that upgrade is concluded with either
+ commit or rollback. Regarding on the scale and complexity of OPNFV system,
+ this requirements looks challenging, however OPNFV implementations should
+ target this with introducing novel designs and solutions.
Pre-upgrading Environment
=========================