-rw-r--r--docs/release/scenario-lifecycle/creating-scenarios.rst104
1 files changed, 104 insertions, 0 deletions
diff --git a/docs/release/scenario-lifecycle/creating-scenarios.rst b/docs/release/scenario-lifecycle/creating-scenarios.rst
new file mode 100644
index 00000000..dbff9c18
--- /dev/null
+++ b/docs/release/scenario-lifecycle/creating-scenarios.rst
@@ -0,0 +1,104 @@
+.. This work is licensed under a Creative Commons Attribution 4.0 International License.
+.. http://creativecommons.org/licenses/by/4.0
+.. (c) 2017 OPNFV Ulrich Kleber (Huawei)
+
+
+Creating Scenarios
+--------------------
+
+General
+^^^^^^^^^
+
+A new scenario needs to be created, when a new combination of upstream
+components or features shall be supported, that cannot be provided with the
+existing scenarios in parallel to their existing features.
+
+Typically new scenarios are created as children of existing scenarios.
+They start as specific scenario and as they mature, they either merge back
+their features to the parent or promote to a generic scenario.
+
+Scenario Owners
+^^^^^^^^^^^^^^^^
+
+Each scenario must have an "owner". Scenario owners have the following responsibilities:
+
+* The scenario owner is responsible for the contents and usage of the scenario.
+* He shall define the contents for the scenario deployment:
+
+ * The components and their versions that need to be deployed
+ * Options for the deployment of such components, e.g. settings, optional features, ..
+ * Which installers to use
+ * Deployment options (HA, NOHA, hardware types, ..)
+
+* He shall define the usage of the scenario in the development process:
+
+ * Initiate integration to CI
+ * Define which testcases to run
+ * Applies that the scenario joins a release
+
+* The owner maintains the Scenario Descriptor File (SDF)
+* Drives for the scenario be supported by more installers
+
+The scenario owner of a specific scenario typically comes from the feature project
+that develops the features introduced by the scenario.
+
+The scenario owner of a generic scenario will need to drive more integration tasks than
+feature development. Thus he typically will come from a project with a broader scope
+than a single feature, e.g. a testing project.
+The scenario owner of a generic scenario needs to cover issues of all installers, so
+only in exceptional cases he will come from an installer project.
+
+Creating Generic Scenarios
+^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
+
+Generic scenarios provide stable and mature deployments of an OPNFV release. Therefore
+it is important to have generic scenarios in place that provide the main capabilities
+needed for NFV environments. On the other hand the number of generic scenarios needs
+to be limited because of resources.
+
+* Creation of a new generic scenario needs TSC consensus.
+* Typically the generic scenario is created by promoting an existing specific
+ scenario. Thus the only the additional information needs to be provided.
+* The scenario owner needs to verify that the scenario fulfills the above requirements.
+* Since specific scenarios typically are owned by the project who have initiated it,
+ and generic scenarios provide a much broader set of features, in many cases a
+ change of owner is appropriate. In most cases it will be appropriate to assign
+ a testing expert as scenario owner.
+
+Creating Specific Scenarios
+^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
+
+As already stated, typically specific scenarios are created as children of existing
+scenarios. The parent can be a generic or a specific scenario.
+
+Creation of specific scenarios shall be very easy and can be done any time. However,
+support might be low priority during a final release preparation, e.g. after a MS6.
+
+* The PTL of the project developing the feature(s) or integrating a component etc can
+ request the scenario (tbd from whom: CI or release manager, no need for TSC)
+* The PTL shall provide some justification why a new scenario is needed.
+ It will be approptiate to discuss that justification in the weekly technical
+ discussion meeting.
+* The PTL should have prepared that by finding support from one of the installers.
+* The PTL should explain from which "parent scenario" (see below) the work will start,
+ and what are the planned additions.
+* The PTL shall assign a unique name. Naming rules will be set by TSC.
+* The PTL shall provide some time schedule plans when the scenario wants to join
+ a release, when he expects the scenario merge to other scenarios, and he expects
+ the features may be made available in generic scenarios.
+ A scenario can join a release at the MS0 after its creation.
+* The PTL should explain the infrastructure requirements and clarify that sufficient
+ resources are available for the scenario.
+* The PTL shall assign a scenario owner.
+* The scenario owner shall maintain the scenario descriptor file according to the
+ template.
+* The scenario owner shall drive the necessary discussions with installers and testing
+ teams to get their support.
+* In case the scenario needs new keywords in the SDF, the scenario owner shall discuss
+ those with the installer teams and CI.
+* The scenario owner shall initiate the scenario be integrated in CI and
+ participate in releases.
+* When the scenario joins a release this needs to be done in time for the relevant
+ milestones.
+
+